03/29/01

VEHICLE MAINTENANCE BUILDING
90% CONSTRUCTION DOCUMENT
Project Area
8748 Square Feet

  99  1100

 

CSI

Description

Total $

Percent

Cost/SF

 

01

General Requirements

45,542

4.23%

5.21

 

02

Site Work

25,845

2.40%

2.95

 

03

Concrete

88,947

8.27%

10.17

 

04

Masonry

132,438

12.32%

15.14

 

05

Metals

87,228

8.11%

9.97

 

06

Wood & Plastics

36,492

3.39%

4.17

 

07

Moisture-Thermal Control

44,197

4.11%

5.05

 

08

Doors, Windows & Glass

61,372

5.71%

7.02

 

09

Finishes

104,792

9.74%

11.98

 

10

Specialties

12,590

1.17%

1.44

 

11

Equipment

91,400

8.50%

10.45

 

12

Furnishings

1,813

0.17%

0.21

 

15

Mechanical

191,056

17.77%

21.84

 

16

Electrical

151,698

14.11%

17.34

 

 

Job total

 

$1,075,412

100.00%

$122.93

 

 

Profit

10%

$107,541

 

 

 

 

Bond

1%

$10,754

 

 

 

 

Contingency

5%

$53,771

 

 

 

 

Grand Total

 

$1,247,478

 

$142.60

 