03/29/01

BUS FUEL AND SERVICE FACILITY
100% CONSTRUCTION DOCUMENT
Project Area
29472 Square Feet

            94  3000

 

 

 

CSI

Description

Total $

Percent

Cost/SF

01

General Requirements

570,953

8.29%

19.37

02

Site Work

1,085,382

15.76%

36.83

03

Concrete

205,161

2.98%

6.96

04

Masonry

531,845

7.72%

18.05

05

Metals

289,563

4.20%

9.83

06

Wood & Plastics

62,436

0.91%

2.12

07

Moisture-Thermal Control

351,293

5.10%

11.92

08

Doors, Windows & Glass

295,621

4.29%

10.03

09

Finishes

95,044

1.38%

3.22

10

Specialties

68,588

1.00%

2.33

11

Equipment

1,441,121

20.92%

48.90

12

Furnishings

4,450

0.06%

0.15

13

Special Construction

204,960

2.98%

6.95

15

Mechanical

799,238

11.60%

27.12

16

Electrical

881,737

12.80%

29.92

 

Job total

 

$6,887,392

100.00%

233.69

 

Profit

6.5%

$447,680

 

 

 

Bond

1%

$68,874

 

 

 

Contingency

3%

$206,622

 

 

 

Grand Total

 

$7,610,568

 

$258.23

*Back