03/29/01

TRAIN STATION
100%CONSTRUCTION DOCUMENT
Project Area
198304 Square Feet

  98  1320

 

CSI

Description

Total $

Percent

Cost/SF

 

01

General Requirements

216,299

7.72%

1.09

 

02

Site Work

1,494,857

53.32%

7.54

 

03

Concrete

406,289

14.49%

2.05

 

04

Masonry

24,190

0.86%

0.12

 

05

Metals

114,460

4.08%

0.58

 

06

Wood & Plastics

15,648

0.56%

0.08

 

07

Moisture-Thermal Control

69,700

2.49%

0.35

 

08

Doors, Windows & Glass

6,263

0.22%

0.03

 

09

Finishes

50,694

1.81%

0.26

 

10

Specialties

27,424

0.98%

0.14

 

13

Special Construction

20,000

0.71%

0.10

 

15

Mechanical

35,024

1.25%

0.18

 

16

Electrical

322,674

11.51%

1.63

 

 

Job total

 

$2,803,522

100.00%

$14.14

 

 

Profit

10%

$280,352

 

 

 

 

Bond

1%

$28,035

 

 

 

 

Contingency

10%

$280,352

 

 

 

 

Grand Total

 

$3,392,261

 

$17.11

 