03/29/01

TRAIN MAINTENANCE FACILITY
100% CONSTRUCTION DOCUMENT

Project Area 46691 Square Feet

  97  2350

 

CSI

Description

Total $

Percent

Cost/SF

            01

General Requirements

1,550,244

10.00%

33.20

02

Site Work

3,140,508

20.25%

67.26

03

Concrete

1,066,287

6.88%

22.84

04

Masonry

147,542

0.95%

3.16

05

Metals

401,247

2.59%

8.59

06

Wood & Plastics

51,367

0.33%

1.10

07

Moisture-Thermal Control

755,626

4.87%

16.18

08

Doors, Windows & Glass

115,145

0.74%

2.47

09

Finishes

174,168

1.12%

3.73

10

Specialties

33,511

0.22%

0.72

11

Equipment

4,152,310

26.77%

88.93

14

Conveying Systems

256,617

1.65%

5.50

15

Mechanical

1,150,017

7.42%

24.63

16

Electrical

2,514,366

16.21%

53.85

 

Job total

 

15,508,954

100.00%

332.16

 

Profit

10%

1,550,895

 

 

 

Bond

1%

155,090

 

 

 

Contingency

5%

775,448

 

 

 

Grand Total

 

17,990,387

 

385.31

*Back