03/29/01

FIRE STATION
60% CONSTRUCTION DOCUMENT
Project Area
6885 Square Feet

  97  2810

 

CSI

Description

Total $

Percent

Cost/SF

01

General Requirements

31,200

4.12%

4.53

02

Site Work

45,766

6.04%

6.65

03

Concrete

60,383

7.97%

8.77

04

Masonry

156,423

20.64%

22.72

05

Metals

3,000

0.40%

0.44

06

Wood & Plastics

69,408

9.16%

10.08

07

Moisture-Thermal Control

52,364

6.91%

7.61

08

Doors, Windows & Glass

42,377

5.59%

6.15

09

Finishes

52,486

6.93%

7.62

10

Specialties

8,593

1.13%

1.25

11

Equipment

37,875

5.00%

5.50

15

Mechanical

85,501

11.28%

12.42

16

Electrical

112,449

14.84%

16.33

 

Job total

 

757,823

100.00%

$110.07

 

Profit

10%

75,782

 

 

 

Bond

1%

7,578

 

 

 

Contingency

10%

75,782

 

 

 

Grand Total

 

916,966

 

$133.18