03/29/01

POLICE HEADQUARTERS
100% CONSTRUCTION DOCUMENT
Project Area
45511 Square Feet

93 2620

 



CSI

Description

Total

Percent

Cost/SF

01

General Requirements

406,008

6.74%

8.92

02

Site Work

746,470

12.39%

16.40

03

Concrete

362,795

6.02%

7.97

04

Masonry

512,179

8.50%

11.25

05

Metals

257,216

4.27%

5.65

06

Wood & Plastics

126,900

2.11%

2.79

07

Moisture-Thermal Control

206,435

3.43%

4.54

08

Doors, Windows & Glass

421,219

6.99%

9.26

09

Finishes

573,779

9.53%

12.61

10

Specialties

127,160

2.11%

2.79

11

Equipment

126,977

2.11%

2.79

13

Special Construction

20,005

0.33%

0.44

14

Conveying Systems

128,000

2.13%

2.81

15

Mechanical

726,646

12.06%

15.97

16

Electrical

1,281,300

21.27%

28.15

 

Job total

 

$6,023,089

100.00%

$132.34

 

Profit

5%

$301,154

 

 

 

Bond

0.95%

$57,219

 

 

 

Contingency

5%

$301,154

 

 

 

Grand Total

 

$6,682,617

 

$146.84

*Back