03/29/01

POST OFFICE
CONSTRUCTION DOCUMENT
Project Area
18506 Square Feet

  99  3150

 

CSI

Description

Total $

Percent

Cost/SF

 

            01

General Requirements

171,101

7.65%

9.25

02

Site Work

187,664

8.39%

10.14

03

Concrete

159,426

7.13%

8.61

04

Masonry

158,702

7.10%

8.58

05

Metals

153,868

6.88%

8.31

06

Wood & Plastics

127,463

5.70%

6.89

07

Moisture-Thermal Control

85,018

3.80%

4.59

08

Doors, Windows & Glass

147,943

6.61%

7.99

09

Finishes

222,702

9.96%

12.03

10

Specialties

51,708

2.31%

2.79

11

Equipment

32,278

1.44%

1.74

12

Furnishings

5,786

0.26%

0.31

13

Special Construction

31,500

1.41%

1.70

15

Mechanical

332,738

14.88%

17.98

16

Electrical

368,820

16.49%

19.93

 

Job total

 

$2,236,717

100.00%

$120.86

 

Profit

10%

$223,672

 

 

 

Bond

1%

$22,367

 

 

 

Contingency

5%

$111,836

 

 

 

Grand Total

 

$2,594,592

 

$140.20