03/29/01

DISTRIBUTION CENTER/WAREHOUSE
CONSTRUCTION DOCUMENT
Project Area
211961 Square Feet

92  0065

 



CSI

Description

Total $

Percent

Cost/SF

01

General Requirements

296,232

3.63

1.40

02

Site Work

867,304

10.63

4.09

03

Concrete

1,242,818

15.24

5.86

04

Masonry

599,823

7.35

2.83

05

Metals

1,290,695

15.82

6.09

06

Wood & Plastics

43,142

0.53

0.20

07

Moisture-Thermal Control

920,082

11.28

4.34

08

Doors, Windows & Glass

120,226

1.47

0.57

09

Finishes

336,992

4.13

1.59

10

Specialties

7,598

0.09

0.04

14

Conveying Systems

40,000

0.49

0.19

15

Mechanical

1,096,967

13.45

5.18

16

Electrical

1,295,082

15.88

6.11

 

Job total

 

$8,156,960

100.00 %

$38.48

 

Profit

5%

$407,848

 

 

 

Bond

1%

$81,570

 

 

 

Contingency

0%

$0

 

 

 

Grand Total

 

$8,646,377

 

$40.79

*Back