03/29/01

BRANCH BANK
CONSTRUCTION DOCUMENT
Project Area
6960 Square Feet

95 3520

 



CSI

Description

Total $

Percent

Cost/SF

01

General Requirements

34,608

6.15%

4.97

02

Site Work

32,007

5.69%

4.60

03

Concrete

5,546

0.99%

0.80

04

Masonry

60,249

10.70%

8.66

05

Metals

20,009

3.55%

2.87

06

Wood & Plastics

45,588

8.10%

6.55

07

Moisture-Thermal Control

15,910

2.83%

2.29

08

Doors, Windows & Glass

37,093

6.59%

5.33

09

Finishes

76,098

13.52%

10.93

10

Specialties

1,624

0.29%

0.23

11

Equipment

1,500

0.27%

0.22

12

Furnishings

5,758

1.02%

0.83

15

Mechanical

128,666

22.86%

18.49

16

Electrical

98,266

17.46%

14.12

 

Job total

 

$562,922

100.00%

$80.88

 

Profit

10%

$56,292

 

 

 

Bond

1%

$5,629

 

 

 

Contingency

5%

$28,146

 

 

 

Grand Total

 

$652,990

 

$93.82