03/29/01

OFFICE BUILDING
CONSTRUCTION DOCUMENT
Project Area
25493 Square Feet

97  1600

 



CSI

Description

Total $

Percent

Cost/SF

01

General Requirements

197,374

5.84%

7.74

02

Site Work

501,738

14.85%

19.68

03

Concrete

290,105

8.58%

11.38

04

Masonry

246,849

7.30%

9.68

05

Metals

338,407

10.01%

13.27

06

Wood & Plastics

249,551

7.38%

9.79

07

Moisture-Thermal Control

166,566

4.93%

6.53

08

Doors, Windows & Glass

145,792

4.31%

5.72

09

Finishes

453,426

13.42%

17.79

10

Specialties

22,359

0.66%

0.88

11

Equipment

2,050

0.06%

0.08

12

Furnishings

9,854

0.29%

0.39

13

Special Construction

3,500

0.10%

0.14

14

Conveying Systems

51,000

1.51%

2.00

15

Mechanical

446,128

13.20%

17.50

16

Electrical

254,930

7.54%

10.00

 

Job total

 

$3,379,629

100.00%

$132.57

 

Profit

8%

$270,370

 

 

 

Bond

1%

$33,796

 

 

 

Contingency

5%

$168,981

 

 

 

Grand Total

 

$3,852,777

 

$151.13