03/29/01

HOSPITAL REHABILITATION CENTER
CONSTRUCTION DOCUMENT NAME
Project Area
232472 Square Feet

92 1300

 

 

CSI

Description

Total $

Percent

Cost/SF

01

General Requirements

3,630,731

9.04%

15.62

02

Site Work

2,159,270

5.37%

9.29

03

Concrete

5,387,441

13.41%

23.17

04

Masonry

3,769,010

9.38%

16.21

05

Metals

1,382,318

3.44%

5.95

06

Wood & Plastics

1,649,422

4.10%

7.10

07

Moisture-Thermal Control

1,126,935

2.80%

4.85

08

Doors, Windows & Glass

2,282,952

5.68%

9.82

09

Finishes

3,800,139

9.46%

16.35

10

Specialties

494,340

1.23%

2.13

11

Equipment

756,045

1.88%

3.25

12

Furnishings

216,850

0.54%

0.93

13

Special Construction

30,241

0.08%

0.13

14

Conveying Systems

1,280,850

3.19%

5.51

15

Mechanical

8,185,520

20.37%

35.21

16

Electrical

4,029,382

10.03%

17.33

 

Job total

 

$40,181,445

100.00%

$172.84

 

Profit

10%

$4,018,145

 

 

 

Bond

1%

$401,814

 

 

 

Contingency

5%

$2,009,072

 

 

 

Grand Total

 

$46,610,476

 

$200.50