03/29/01

MIDDLE SCHOOL GYM
DESIGN DEVELOPMENT ESTIMATE
Project Area
11830 Square Feet

92  0211

 



CSI

Description

Total $

Percent

Cost/SF

02

Site Work

5,587

0.51%

0.47

03

Concrete

154,846

14.05%

13.09

04

Masonry

313,102

28.40%

26.47

05

Metals

49,015

4.45%

4.14

06

Wood & Plastics

12,609

1.14%

1.07

07

Moisture-Thermal Control

61,630

5.59%

5.21

08

Doors, Windows & Glass

16,143

1.46%

1.36

09

Finishes

115,068

10.44%

9.73

10

Specialties

16,000

1.45%

1.35

11

Equipment

74,250

6.73%

6.28

15

Mechanical

168,815

15.31%

14.27

16

Electrical

115,385

10.47%

9.75

 

Job total

 

$1,102,450

100.00%

$93.19

 

Profit

8%

$88,196

 

 

 

Bond

1%

$11,025

 

 

 

Contingency

5%

$55,123

 

 

 

Grand Total

 

$1,256,793

 

$106.24