03/29/01

UNIVERSITY FOUNDATION BUILDING
75% CONSTRUCTION DOCUMENT
Project Area
10648 Square Feet

  99  3510

 

CSI

Description

Total $

Percent

Cost/SF

 

01

General Requirements

62,500

3.81%

5.87

 

02

Site Work

297,446

18.13%

27.93

 

03

Concrete

69,214

4.22%

6.50

 

04

Masonry

97,778

5.96%

9.18

 

05

Metals

24,305

1.48%

2.28

 

06

Wood & Plastics

339,405

20.69%

31.88

 

07

Moisture-Thermal Control

66,124

4.03%

6.21

 

08

Doors, Windows & Glass

107,712

6.57%

10.12

 

09

Finishes

185,158

11.29%

17.39

 

10

Specialties

4,071

0.25%

0.38

 

11

Equipment

9,000

0.55%

0.85

 

14

Conveying Systems

60,000

3.66%

5.63

 

15

Mechanical

189,984

11.58%

17.84

 

16

Electrical

127,903

7.80%

12.01

 

 

Job total

 

$1,640,601

100.00%

$154.08

 

 

Profit

10%

$164,060

 

 

 

 

Bond

1%

$16,406

 

 

 

 

Contingency

10%

$164,060

 

 

 

 

Grand Total

 

$1,985,127

 

$186.43

 