03/29/01

ART MUSEUM RENOVATION
 CONSTRUCTION DOCUMENT
Project Area
1912 Square Feet

95 0220

 



CSI

Description

Total $

Percent

Cost/SF

01

General Requirements

51,744

12.39%

27.06

02

Site Work

85,512

20.47%

44.72

03

Concrete

20,152

4.83%

10.54

04

Masonry

40,015

9.58%

20.93

05

Metals

61,027

14.61%

31.92

06

Wood & Plastics

12,420

2.97%

6.50

07

Moisture-Thermal Control

13,031

3.12%

6.82

08

Doors, Windows & Glass

31,263

7.49%

16.35

09

Finishes

47,043

11.26%

24.60

15

Mechanical

30,592

7.32%

16.00

16

Electrical

24,856

5.95%

13.00

 

Job total

 

$417,656

100.00 %

$218.44

 

Profit

10%

$41,766

 

 

 

Bond

1%

$4,177

 

 

 

Contingency

10%

$41,766

 

 

 

Grand Total

 

$505,363

 

$264.31