03/29/01

ELDERLY HOUSING/
ASSISTED LIVING 6 Story
CONSTRUCTION DOCUMENT
Project Area
64560 Square Feet

97 1400


CSI

Description

Total $

Percent

Cost/SF

01

General Requirements

298,676

4.98

4.63

02

Site Work

181,951

3.04

2.82

03

Concrete

511,951

8.54

7.93

04

Masonry

584,288

9.75

9.05

05

Metals

181,767

3.03

2.82

06

Wood & Plastics

379,209

6.33

5.87

07

Moisture-Thermal Control

295,007

4.92

4.57

08

Doors, Windows & Glass

437,192

7.30

6.77

09

Finishes

750,945

12.53

11.63

10

Specialties

34,038

0.57

0.53

11

Equipment

105,350

1.76

1.63

12

Furnishings

2,577

0.04

0.04

13

Special Construction

15,395

0.26

0.24

14

Conveying Systems

168,000

2.80

2.60

15

Mechanical

1,238,997

20.68

19.19

16

Electrical

806,840

13.46

12.50

 

Job total

 

$5,992,185

100.00%

$92.82

 

Profit

5%

$299,609

 

 

 

Bond

1%

$59,922

 

 

 

Contingency

2%

$119,844

 

 

 

Grand Total

 

$6,471,560

 

$100.24