03/29/01

PARKING GARAGE
DESIGN DEVELOPMENT ESTIMATE
Project Area
57388 Square Feet

  98  1100

 

CSI

Description

Total $

Percent

Cost/SF

01

General Requirements

94,029

5.70%

1.64

02

Site Work

243,895

14.80%

4.25

03

Concrete

903,485

54.81%

15.74

04

Masonry

110,975

6.73%

1.93

05

Metals

32,332

1.96%

0.56

06

Wood & Plastics

10,818

0.66%

0.19

07

Moisture-Thermal Control

55,701

3.38%

0.97

08

Doors, Windows & Glass

28,651

1.74%

0.50

09

Finishes

7,494

0.45%

0.13

10

Specialties

4,742

0.29%

0.08

11

Equipment

5,785

0.35%

0.10

15

Mechanical

32,623

1.98%

0.57

16

Electrical

117,954

7.16%

2.06

 

Job total

 

$1,648,485

100.00%

$28.73

 

Profit

10%

$164,849

 

 

 

Bond

1%

$16,485

 

 

 

Contingency

10%

$164,849

 

 

 

Grand Total

 

$1,994,667

 

$34.76