03/29/01

PUBLIC LIBRARY
DESIGN DEVELOPMENT ESTIMATE
Project Area
30237 Square Feet

  00  0750

 

CSI

Description

Total $

Percent

Cost/SF

01

General Requirements

275,688

9.82%

9.12

02

Site Work

419,897

14.95%

13.89

03

Concrete

145,418

5.18%

4.81

04

Masonry

214,536

7.64%

7.10

05

Metals

82,045

2.92%

2.71

06

Wood & Plastics

211,300

7.52%

6.99

07

Moisture-Thermal Control

154,464

5.50%

5.11

08

Doors, Windows & Glass

237,935

8.47%

7.87

09

Finishes

288,592

10.27%

9.54

10

Specialties

12,060

0.43%

0.40

11

Equipment

5,000

0.18%

0.17

12

Furnishings

14,417

0.51%

0.48

13

Special Construction

74,880

2.67%

2.48

14

Conveying Systems

60,000

2.14%

1.98

15

Mechanical

375,574

13.37%

12.42

16

Electrical

237,011

8.44%

7.84

 

Job total

 

$2,808,820

100.00 %

$92.89

 

Profit

10%

$280,882

 

 

 

Bond

1%

$28,088

 

 

 

Contingency

10%

$280,882

 

 

 

Grand Total

 

 

$3,398,672

 

 

$112.40

*Back