03/29/01

MEMORIAL LIBRARY
90% CONSTRUCTION DOCUMENT
Project Area
62479 Square Feet

  96  5130

 

CSI

Description

Total $

Percent

Cost/SF

01

General Requirements

486,197

6.20%

7.78

02

Site Work

659,046

8.41%

10.55

03

Concrete

457,051

5.83%

7.32

04

Masonry

539,479

6.88%

8.63

05

Metals

900,742

11.49%

14.42

06

Wood & Plastics

561,195

7.16%

8.98

07

Moisture-Thermal Control

566,264

7.22%

9.06

08

Doors, Windows & Glass

648,460

8.27%

10.38

09

Finishes

896,003

11.43%

14.34

10

Specialties

44,869

0.57%

0.72

11

Equipment

12,000

0.15%

0.19

12

Furnishings

17,781

0.23%

0.28

13

Special Construction

75,000

0.96%

1.20

14

Conveying Systems

105,000

1.34%

1.68

15

Mechanical

1,226,603

15.65%

19.63

16

Electrical

642,628

8.20%

10.29

 

Job total

 

$7,838,319

100.00%

$125.46

 

Profit

10%

$783,832

 

 

 

Bond

1%

$78,383

 

 

 

Contingency

10%

$783,832

 

 

 

Grand Total

 

$9,484,366

 

$151.80