03/29/01

MILITARY ADMINISTRATION BUILDING
CONSTRUCTION DOCUMENT
Project Area
16495 Square Feet

  96  8600

 

CSI

Description

Total $

Percent

Cost/SF

01

General Requirements

266,066

9.82%

16.13

02

Site Work

352,609

13.01%

21.38

03

Concrete

32,887

1.21%

1.99

04

Masonry

69,326

2.56%

4.20

05

Metals

30,066

1.11%

1.82

06

Wood & Plastics

39,044

1.44%

2.37

07

Moisture-Thermal Control

110,434

4.08%

6.70

08

Doors, Windows & Glass

89,803

3.31%

5.44

09

Finishes

228,205

8.42%

13.83

10

Specialties

14,558

0.54%

0.88

11

Equipment

679

0.03%

0.04

12

Furnishings

284,074

10.48%

17.22

13

Special Construction

4,070

0.15%

0.25

15

Mechanical

746,437

27.55%

45.25

16

Electrical

441,434

16.29%

26.76

 

Job total

 

$2,709,693

100.00%

$164.27

 

Profit

6%

$162,582

 

 

 

Bond

1%

$27,097

 

 

 

Contingency

5%

$135,485

 

 

 

Grand Total

 

$3,034,857

 

$183.99